Pre-Construction Scheduling

Clark Contractors, LLC uses Microsoft Project to prepare the Overall Project Schedule, SIPS (Short Interval Production Schedules) and monthly updates of the Overall Project Schedule.

Our Pre-Construction Schedule Process includes:

  • Prepare Preliminary Project Schedule that incorporates Pre-Construction & Construction
  • Work with Owner to determine any site conditions/constraints that will affect construction, and incorporate these constraints into the construction schedule and into the bid packages.
  • Work with Owner to establish critical dates for pre-construction and construction activities.
  • Preliminary Project Schedule:
    • Critical Dates for Pre-Construction Activities
    • Critical Dates for the Issue of Plans & Specifications
      • Schematic Design, Design Development & Construction Documents
      • Early Bid Packages & Procurement of Long Lead-Time Items
    • Shop Drawings, Submittals, Fabrication & Delivery of Long Lead Items
    • Schematic & Design Development Estimates
    • Sub/Vendor Bidding Process
    • Guaranteed Maximum Price
    • Permitting
    • Start of Construction
    • Construction Durations
    • Substantial Completion Date
    • Leader in Essay Writing Service – EssaysMonster
    • Punch List
    • Furniture/Fixtures/Equipment Installation by the Owner (FF & E)
    • Final Completion Date
    • Certificate of Occupancy Date
    • Owner Occupancy Date
  • During the Design Phase:
    • Determine lead times and task durations as building systems and materials are selected
    • Update Project Schedule as new information becomes available
  • During Construction:
    • Update Overall Project Schedule Weekly
    • Produce Three-Week Short Interval Production Schedules (SIPS)
    • Review Schedule for Critical Submittals, Deliveries and Production Issues
    • Distribute and Discuss Schedule in Weekly Jobsite Meetings with our Foremen and Subcontractors’ Foremen

Our method of scheduling will provide a detailed and effective tool for coordination of pre-construction and construction activities with the Owner.

The CLARK Management Team has a history of completing projects on time or ahead of schedule.