Good Day Farm Pine Bluff Cultivation and Processing Facility

This project involved a 101,319 SF renovation of a former drum and container warehouse to accommodate Good Day Farm’s rapidly expanding operations, including a 42,000 SF canopy facility for growing crops.

This $24.5 million project was completed on an accelerated, fast-track schedule, with construction completed in 4.5 months, or an average of 845 SF finished per day. The type of schedule required the team to strategically plan through lead times on equipment and materials.

The project was completed in two phases. The first phase was for the 62,000 SF Cultivation Building and was essentially a phase within a phase. The main priority in the first phase was the vegetation rooms. The second phase was the 34,000 SF Processing Building, which houses the vault, extraction, and packaging. In addition, over 1,800 tons of HVAC were added between the two buildings.

 

 

 

Project Details

Client

Good Day Farm

Location

Pine Bluff, Arkansas

Architect

TreanorHL

Completion Date

April 2021